| Day 1 - Wednesday, 5 April |
|
8:00 | Registration |
|
|
| Morning Sessions will be led by |
| Sr. Noushad Ali Naseem bin Ameer Ali |
| FISM, MRICS, MAPM, MCIArb, FCIOB, RegQS, Accredited Mediator [CIDB Panel] BSc (Hons) QS [Reading], CDipAF, MSc Arch [UCL], MSc Construction Law (KCL) |
| Director |
| HPRC Consulting Group (M) Sdn Bhd |
| Managing Director |
| CIC-QS Services Sdn Bhd |
|
9:00 | CONTRACT DRAFTING AND FORMATION |
| • Basic principles of formation of construction contracts |
| • Allocating risk between parties to a contract |
| Standard forms of construction contracts in Malaysia |
| • Amended standard forms of construction contracts – illustrations from PAM 98, JKR 203A and CIDB 2000 contracts |
| • Alternative construction contract strategies – a contract in plain English that the client, contractor and contract administrator truly understand |
|
10:00 | CERTIFICATION FOR PAYMENT IN THE CONSTRUCTION INDUSTRY – THEORY VS. REALITY |
|
10:30 | Discussion followed by Coffee |
|
10:50 | THE EXTENT OF PAYMENT PROBLEMS IN THE CONSTRUCTION INDUSTRY |
| • Consultants’ Perspective |
| • Contractor’s Perspective |
| • Supplier’s Perspective |
|
11:30 | PAY-WHEN-PAID AND PAY-IF-PAID CLAIMS |
|
12:00 | HOW STATUTORY INTERVENTION HELPS THE CONSTRUCTION INDUSTRY MOVE TOWARDS ZERO PAYMENT DEFAULT – A MALAYSIAN CONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT |
|
1:00 | Discussion followed by Lunch |
|
|
| Afternoon Session led by |
| Alastair Gray |
| Senior Consultant |
| Trett Consulting |
|
2:00 | ACCELERATION & PRODUCTIVITY LOSS |
| • Reasons for acceleration |
| • “Constructive acceleration” |
| • Dilemma’s of acceleration for Contractors and Employers |
| • The effects on productivity and key problems |
| • Demonstrating acceleration & productivity loss |
|
3:15 | Discussion followed by Tea |
|
3:45 | EXTENSION OF TIME ANALYSIS - MYTHOLOGY & METHODOLOGY |
| • Background of delay and the approach of the courts both past & present |
| • Demonstration of delay using various methods of delay analysis techniques |
| • Comparison of methods of delay - relative strengths and weaknesses |
| • Practicalities of making and resisting delay claims |
| • Case study |
|
5:00 | Discussion followed by Close of Day One |
|
|
| Day 2 - Thursday, 6 April |
|
|
| Sessions led by |
| Sanjay Mohannasundaram |
| Partner |
| Lee Hishammuddin Allen Gledhill |
|
|
| SUBCONTRACTING |
|
|
| CLAIMS MANAGEMENT |
| • Claims for liquated damages |
| • Claims for defective works |
| • Claims for damages under other express provisions of construction contracts |
|
|
| VARIATIONS |
| • The right for one party to unilaterally vary the contract provisions |
| • Procedural pre-requisites |
| • Types of variations |
| • Assessing and valuing variation claims |
|
|
| DISPUTE RESOLUTION |
| • Negotiation |
| • Mediation / Conciliation |
| Adjudication |
| • Arbitration |
| • Litigation |
|
5:00 | Final Discussion followed by Close of Program |
|
|
| Day Two Sessions are from 9.00am – 5.00pm, Coffee at 10.30 – 11.00, Lunch at 1.00 – 2.00, Tea at 3.30 – 4.00. All breaks are subject to the discretion of the Speaker, depending on the flow of the program) |